Montreal, QC, Canada
510-ft. (155.5-meters) highway bridge (3 spans)
2011-2012
2012
G.T.S. (Les Grands Travaux Soter Inc.)
CIMA +
Quebec Ministry of Transportation
Fabrication of the steel bridge superstructure (910 tons)
10 box girders
Girders measure between 93 and 119 ft. (28.3 and 36.3 m) in length
Girders weigh between 85,000 and 130,000 lbs. (38,555 and 58,967 kg) a piece
Metallizing
Goodco Z-Tech:
8 elastomeric pot bearings
32 laminated bearings
1 LG-2 modular expansion joint
3 HSS expansion joints
Construction of an overpass in the scope of the Des Laurentides Interchange rehabilitation project in Montreal, Quebec.
Delivery of the components took place over a five-day period and 10 cranes were required for the erection of girders which was completed in one single night.